What should be the depth of removal of rock encountered in trenching?

  1. At least one foot below the grade line

  2. Up to the grade line

  3. At least three inches below the grade line

  4. Exactly at the grade line

The correct answer is: At least three inches below the grade line

The correct depth for the removal of rock encountered in trenching is at least three inches below the grade line. This practice is essential because it provides a stable base for the installation of utilities, such as pipes or conduits, ensuring that they are not subjected to undue stress from surrounding rock. Removing rock to this depth allows for proper bedding material to be placed, which helps with drainage and prevents movement that could compromise the integrity of the installation. The specification of at least three inches ensures that any irregularities in the rock are addressed, preventing potential future issues from occurring due to shifting or settling of the surrounding soil. This adherence to depth standards is crucial for maintaining the functionality and longevity of the installed utilities. Additionally, being too close to the grade line may leave insufficient room for necessary adjustments or for the addition of protective materials, while removing rock deeper than three inches may lead to unnecessary excavation, increasing costs and potentially causing instability in the surrounding soil structure.