Massachusetts Plumbers Journeyman Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the Massachusetts Plumbers Journeyman Exam. Prepare with multiple choice questions, hints, and detailed explanations. Ace your licensing exam with confidence!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


When should the Inspector make an inspection upon notice of a request for the rough plumbing?

  1. Immediately after receipt of such notice

  2. Within one working day after receipt of such notice

  3. Within two working days after receipt of such notice

  4. Within three working days after receipt of such notice

The correct answer is: Within two working days after receipt of such notice

The correct answer highlights the importance of timely inspections in the plumbing process. The requirement to conduct the inspection within two working days after receiving notice of a rough plumbing request balances the need for prompt action with the practical considerations of scheduling and workload for the inspector. This timeframe allows inspectors to manage their responsibilities effectively while ensuring that plumbing work can proceed without unnecessary delays. It is critical for maintaining an efficient workflow in construction and plumbing projects, ensuring that inspections do not hold up progress more than necessary. The two-day window ensures that all parties involved have reasonable expectations regarding the timing of the inspection, while also accommodating potential scheduling conflicts that may arise. The other options suggest timelines that are either too immediate or too extended, which may not align with the best practices for maintaining project momentum and compliance with regulations.